Building Safety Levy in Hounslow

Hounslow is the 21th most expensive of 298 English collecting authorities. The greenfield area rate is £58.29/m², halved to £29.15/m² where ≥75% of the red-line boundary qualifies as previously developed land. BSL commences 1 October 2026 and is collected by Hounslow at building-control and commencement stages.

Rates for Hounslow

Rate type£ per m² GIAApplies when
Greenfield (standard)£58.29Less than 75% of site is previously developed land
Brownfield (PDL discount)£29.15≥75% of site is previously developed land (any building since July 1948, excluding agriculture)

Source: Schedule 3, Building Safety Levy (England) Regulations 2025, effective 1 October 2026.

Example scheme costs in Hounslow

SchemeTotal chargeable GIA Greenfield levyBrownfield levyPDL saving
10 dwellings at 85 m² each (small infill)850 m²£49,546£24,778£24,769
50 dwellings at 100 m² each (typical phase)5,000 m²£291,450£145,750£145,700
100 dwellings at 95 m² each (mid-size scheme)9,500 m²£553,755£276,925£276,830
200 dwellings at 90 m² each (major development)18,000 m²£1,049,220£524,700£524,520

All examples assume 100% residential with no communal-area adjustments. Real schemes will differ based on communal floorspace, PBSA bedspaces, and exemptions.

The 50% brownfield discount

For a typical 50-dwelling scheme in Hounslow, successfully evidencing previously developed land status saves £145,700 in levy. That’s the whole point of the PDL evidence workflow — the statutory definition (any building on the site since 1 July 1948, excluding agriculture) is broader than the local brownfield register, and most sites qualify in full or in part when historic OS maps and aerial imagery are reviewed.

Run your scheme through the calculator →

Related authorities

Similar rates or alphabetically adjacent:

Kingston upon Thames £57.68Merton £59.02Redbridge £57.02Southwark £56.93Hinckley and Bosworth £26.79Horsham £41.57Huntingdonshire £29.12Hyndburn £14.83

Submitting your BSL information to Hounslow

BSL submissions happen in two stages: (1) at your building-control application, and (2) at your first commencement notice. Hounslow has five weeks from your commencement notice to assess and issue a liability notice. Any GIA or PDL discrepancy can delay commencement.

BSL Prep extracts chargeable GIA from your architectural PDFs, compiles the PDL evidence pack, and produces the submission proforma for Hounslow in one click. See pricing →